Notice of website discontinuation following termination of GAC activities in Guinea on 23 August 2025

 

This website is no longer being updated following the termination of GAC activities in Guinea on 23 August 2025.

 

All content here reflects information published prior to the termination of GAC activities on 23 August 2025. It does not represent any activities or positions thereafter and remains online for archival purposes only.

 

GAC connects its rail spurs to existing railway lines

Guinea Alumina Corporation (GAC) SA, a major contributor in the mining sector in Guinea, today announced the completion of work to connect its railway spurs at Kamsar with the existing railway line between the mining area north of Sangaredi and the...

GAC connects its rail spurs to existing railway lines


Guinea Alumina Corporation (GAC) SA, a major contributor in the mining sector in Guinea, today announced the completion of work to connect its railway spurs at Kamsar with the existing railway line between the mining area north of Sangaredi and the coast.

The completion of railway connections is another milestone in the development of GAC’s bauxite mine and export project. GAC’s project is one of the largest greenfield investments in Guinea in the past 40 years and first bauxite exports are expected during the second half of 2019.

The team responsible for performing the railway connection work was made of some 1,000 people of which 90% were nationals and was completed safely and on schedule. Bauxite from GAC’s mine will be transported to the rail by coast, using existing railway lines.

GAC’s production is expected to ramp up to some 12 million tonnes of bauxite per year.

This railway connection work included the completion of two receiving tracks plus an outgoing track at the port facility, completing the rail transport infrastructure needed for operations at Kamsar.

Steeve Tremblay, Project Director at GAC, said: “Completing this transport infrastructure is a huge achievement for the team, and a major step towards first bauxite. This infrastructure is critical for us to deliver value to our shareholders and Guinea for decades to come and I am pleased that we completed this work safely and on schedule.”

More than 3,200 Guineans, almost 80 per cent from the Boké region, are currently working to construct the Guinea Alumina Corporation project. GAC has a total budgeted project cost of approximately $1.4 billion.

GAC is a wholly-owned subsidiary of Emirates Global Aluminium, which was the world’s largest ‘premium aluminium’ producer in 2017.

You may also be interested in

GAC and Chalco agree to explore cooperation on development of alumina refining in Guinea

Guinea Alumina Corporation and Aluminium Corporation of China (Chalco), have agreed to explore cooperation on the development of alumina refining in the Republic of Guinea.

Read more

Another step forward in GAC’s commitment to skills development and positive socio-economic impact

Guinea Alumina Corporation S.A. (GAC), today announced that it has completed another important step in its Project 150 programme.

Read more

GAC reviews its policy on employment

GAC reviews its policy on employment Guinea Alumina Corporation (GAC SA), a major player in the mining sector in the Republic of Guinea, communicated on 18 August 2017, its balance sheet in terms of employment and training since the beginning of...

Read more